| Case study 4: Oyster - serve rack move |
|||||
| Server Rack Relocation This London based client was merging with another company, also based within the Capital, and had already moved the PC’s themselves the weekend before, but required Technimove to safely relocate their 2 Server racks. A pre-move survey highlighted that the height of the two Server racks would prevent them from entering the lift, and the staircase was too narrow to walk them down. This meant that they had to be lowered by use of a hoist, from their 1st floor location. A Project Manager for this move, which took
place on Saturday, oversaw a team The kit was loaded on the vehicle and safely transported to its new location. Upon arrival, the team unloaded the vehicle and began recommissioning the two Servers. The Server Engineer on site again assisted the clients’ I.T. staff in bringing the Servers back up on line. The team finished ahead of schedule |
![]() |
||||
![]() |
|||||
![]() |
|||||
![]() |
|||||